Frequently Asked Questions

Provided below are answers to often-asked questions about the Briding Method. If you have a question that is not addressed here, please contact us with your question and we will publish it on this website as soon as feasible.

Can an A/E's traditional Design Development documents be used for bids or negotiation for a Bridging type design-build contract?

No. In fact, that is a course some have taken by mistake thinking they were doing Bridging, but it is an approach that will lead to many problems for both the owner and the design architect. The“Design Guide Illustrations” and the“Owner’s Minimum Requirements” are the drawings and specifications of the bidding documents (final pricing documents) in a Bridging project. These drawings and specifications would be developed and prepared after traditional Schematic Design is completed and approved. These drawings ("DGIs”) and specifications ("OMR”) along with forms of contract, etc, make up the Bridging Contract Documents. The level of effort by the Owner’s Design Consultant (who might be referred to as the Bridging Architect or the Design Architect) is about the same as that in design development documents --- depending on the project objectives --- but they are quite different from traditional design development phase drawings and specifications. Typically, the architectural drawings and design decisions are much more advanced than in traditional “DDs”, but the engineering drawings are fewer, though there will have been extensive consultation with the architects by the consulting engineers and there will be sufficient performance and some prescriptive specifications for the engineered systems of the project. The basic idea is to design, illustrate and specify everything that needs to be tied down to fully protect both the owner and the design but to leave as much latitude as possible to design-build bidders to use their skills and experience to give the owner the best buy. A couple of examples: There are likely to be no drawings and few specifications other than code compliance for the foundations, but finish hardware must be fully scheduled and specified at the 100% CD level. Another example would be the plumbing system for which performance specifications with a few prescriptive requirements might be sufficient in most projects for the plumbing system except for fixtures and fittings. But all plumbing fixtures, fittings, floor drains, etc. must be fully specified and located on the floor plans and in interior elevations. To learn more about this, please view Chapter 5 of the Step-by-Step section.

Return to Top of Page

In a Bridging project, doesn't it cause confusion for there to be two designers?

In a Bridging project there is only one architectural designer, the Owner’s Design Consultant (“ODC”) sometimes referred to as the Bridging Architect or the Design Architect. That designer should make and document all of the design decisions that are needed to protect the owner and the design. The MEPSC consulting engineers who are part of the ODC’s team will consult with the ODC, probably make some of the DGIs, and will prepare appropriate performance specifications with some prescriptive specifications. One of the major roles of the Contractor's architects and engineers (which are subcontractors to the contractor), is to produce a complete, accurate, coordinated and code compliant set of final Construction Documents in full accordance with the Bridging Contract Documents and its DGIs and OMR prepared by the Owner’s Design Consultant.

Return to Top of Page

Doesn’t Bridging limit the level of control over design and construction quality?

No. The Owner’s Design Consultant (“Bridging Architect” or “Design Architect”) can and should use its professional judgment as to what is “tied down” and what is not. If in doubt, a greater degree of completeness and specificity is the proper course. Keep in mind that the degree to which latitude is taken away from the design-build proposers may effect the cost to the owner.

Return to Top of Page

In a Bridging project, who is the Architect-of-Record, the Owner’s Design Consultant or the Contractor’s AE?

The Contractor’s architects and engineers are the Architects of Record and the Engineers of Record.

Return to Top of Page

Are the bids or negotiated prices that are received and which are based on the Bridging Contract Documents subject to adjustment upon completion of the Construction Documents?

Not unless the owner has elected to make changes. The price received on Bridging Contract Documents --- which is at a much earlier stage in the design and construction sequence and resulting in a lower “front end” at-risk cost to the owner --- is at least as enforceable as a price based on final Contract Documents in the traditional method. The reason it is enforceable is the same reason that a GMP issued based on Design Development documents is not readily enforceable. The Contractor will not be able to claim, after the award of the Bridging type contract, that the contractor had no way of knowing all of the things that the owner’s architect and engineers were going to include or add, detail and specify. Further, the Contractor will not be entitled to any adjustment for price escalation after award or for building permitting issues if there have been no changes in the applicable codes. If the Owner does elect to make changes, that would be the basis of a change order as in a traditional contract.

Return to Top of Page

Isn’t it rather disjointed for the Bridging Architect to hand off the project at the end of preparation of the Bridging Contract Documents?

There is no “hand off” by the Bridging Architect. Unless the owner chooses another course, the ODC would continue to provide services to the Owner throughout the project. After assisting in the design and award phase, the ODC would review the Construction Documents for compliance with the Bridging Contract Documents, and the ODC would have the leverage of approving or disapproving payment to the Contractor for the satisfactory completion of the Construction Documents. Those services, along with the normal construction phase observation of the Work and recommendations on payments, as well as processing change orders, and assistance to the Owner in the administration of the contract between the Owner and the Contractor will be performed by the ODC.

Return to Top of Page

Doesn’t Bridging cause the owner to have higher architectural and engineering fee costs since there are two AEs?

No. For full services through design and construction phases, the Owner’s Design Consultant (“Bridging Architect” or “Design Architect”) would typically be compensated about 60-65% of a normal AE fee. The Contractor will typically compensate the Contractor’s AE about 35-40% of a normal AE fee for the preparation of the Construction Documents

Return to Top of Page