Posts Tagged ‘contract’

Bridging Method Phase 2

Thursday, January 28th, 2010

Bridging Method Phase 2

PHASE 2 OF CARRYING OUT A PROJECT BY THE BRIDGING METHOD IS CRITICALLY IMPORTANT AND SETS THE METHOD APART FROM OTHER METHODS

Phase 2. Design work and specifying done in this phase are referred to as the preparation of the Bridging Contract Documents (BCDs) and involve the ODC developing all important and critical aspects of the architectural design including at least the controlling details of the design. This design work and document preparation for a Bridging project is carried out at the same point in the sequence of design as the Design Development phase of services in the traditional Design-Bid-Build with about the same or somewhat greater overall level effort as in the production of typical Design Development (“DD”) documents. However, the Bridging Contract Documents (BCDs) are substantially different from DD documents. Use of typical DD documents at this point will probably cause (more…)